Large load, without the heatmap

A data center or other large load is a customer problem before it is a map problem. This hub is the Florida example: the 2026 statute and Florida Power & Light's large-load schedules, linked to the documents that say who counts, what they may have to pay for, and what the utility still has to study. It does not rank sites. Other registered states are on state coverage. A state that is not listed there is not covered.

Start here

Two clocks and two intervals

The statute's large load customer test uses the highest 15-minute average. The tariff's billing demand uses 30 minutes. Load factor is a third measurement, and on the LLCS sheets the company determines the projected figure. Mixing them is how a confident answer goes wrong.

Open questions

Does Grid Accord tell me if a site has power available?

No. Capacity status is not determined. A class cap, a nearby line, or a county name is not spare megawatts.

Is a requested in-service date a forecast?

No. The date is stored as a request. The LLCS agreement says an estimate still depends on facilities and generation.

Does failing the 85 percent load factor end the statutory question?

No. Section 366.043 uses a 15-minute peak and does not create an 85 percent exemption. The screen keeps that comparison separate when the interval is 15 minutes.

Is this utility advice?

No. Evidence, not advice. This hub is a Florida example. A production-mode request returns production_disabled. Registered states are on the coverage page.

Docket 20260149-EI is recorded in the November 8, 2026 assessment as a compliance proceeding, not a finished finding. The hearing window in that assessment is May 4–7, 2027. Waiting for that hearing is not treated here as a reason to pretend the existing schedules do not exist. Details and links are on the source register.