Cluster
CIAC, without a calculator
Contribution in aid of construction is money a customer pays toward facilities. On the LLCS agreement form, CIAC payments are due within 45 days, calculated under the tariff in effect at payment. The form says a failure to pay on time can make the agreement and the associated studies void, and that construction does not have to start before payment. LLCS agreement, Sheet 9.969, section 12
Order No. PSC-2026-0265-TRF-EI, issued July 28, 2026, approves CIAC tariff edits effective 30 days after the July 7, 2026 vote. The sheet language in that order says a non-governmental applicant whose new or upgraded facilities are estimated at $50 million or more advances the estimated work-order cost, with a monthly refund or credit pattern that does not run past five years. Consummating order PSC-2026-0300-CO-EI, issued August 24, 2026, says 0265 became effective and final and that the docket shall be closed. PSC-2026-0265-TRF-EI PSC-2026-0300-CO-EI
Two dates are not reconciled here. The sheet image inside the July 28 order still prints an Effective January 1, 2026 footer. A November 8, 2026 assessment of the issued Second Revised Sheet 6.199 records an August 6, 2026 effective date, which matches 30 days after July 7. The older as-filed 15 MW trigger discussed in the rate-case order is not treated as the current rule. Utility estimates needed for a final figure are not in this screen, so no CIAC amount is computed. FPL tariff Section 6
Related: large-load hub, glossary, source register, try a screen.