A 3 GW class cap is not spare power

llcs-1 · capacity

Sheet 8.950 says service under LLCS-1 applies up to a class combined total of 3 GW, and that the schedule closes to new or incremental load when that cap is fully subscribed. The sentence caps a rate class. It does not say how much of that class is unsubscribed, and it does not say a particular site can be served.

A screen that prints the cap next to a county, or next to a line someone noticed on a map, is still not a capacity study. Sheet 9.964, definition 2.52, says the system studies determine capacity availability, including amount and timing. Until those studies exist, the honest capacity line is not determined.